Ambient Station Monitoring in Power Plant

Executive Summary

Customer Name: Saudi Electric Company implemented via Gulf Advanced Control Systems (GACS)

Focus: Setting up aggregator online monitoring system for Ambient stations and stacks

BUSINESS CHALLENGE

  • To install and operate a server at each plant connecting to multiple stacks and ambient stations which will be the aggregator for pollution data
  • To generate relevant alarms/ alerts and warnings based on real time data

SOLUTION

  • EnviroConnect is a ready to deploy solution with full and advanced functionality, dash board based viewing, evolved alarms and alerts management and powerful reporting 
  • Based on the project objectives and technical requirements put up by ‘Presidency of Meteorology and Environment (PME)’ office, GACS evaluated and selected EnviroConnect as the most appropriate solution for the project

BUSINESS RESULTS

  • The system is in operations since last 1.5 years
  • EnviroConnect has strong server component to handle large data load

Customer Background

Gulf Advanced Control Company (GACS) is an engineering company from United Kingdom of Saudi Arabia selling and servicing instruments for monitoring of ambient air quality, continuous emissions, particulates, water quality, oil spill monitoring and laboratory instrumentations. It has large number of installations across Saudi Arabia and the Middle East in various industries like cement, power, textile mills, etc.

GACS bagged a prestigious order from Saudi Electric Company Organization (SECO) to connect multiple stacks, ambient stations and ETP stations and monitor it online.

Environmental Standards in Saudi Arabia

The Environmental Protection Standards in Saudi Arabia are implemented by ‘Presidency of Meteorology and Environment (PME)’ since 1982. As per the guidelines of PME, SECO came up with the tender for online data monitoring and connecting Ambient stations and Stacks in each plant. In the next phase ETP stations will be connected and data will be collected online.

Business Requirements

  • To install and operate a server at each plant connecting to multiple stacks and ambient stations which will be the aggregator for  pollution data
  • To collect the data in real time
  • To store and archive all data for analysis and reporting
  • To generate relevant alarms/ alerts and warnings based on real time data
  • To provide additional functionality for authorized users for data management and analysis as well as for generating reports
  • Report generation and distribution as per configuration

EnviroConnect Solution

GACS selected EnviroConnect for its easy to deploy features, quality and compliance with Saudi Arabia Environment rules and regulations.Based on the project objectives and technical requirements put up by ‘Presidency of Meteorology and Environment (PME)’ office, GACS evaluated and selected EnviroConnect as the most appropriate solution for the project. Main reasons for this selection were:

  • EnviroConnect was a ready solution with all required functionality
  • EnviroConnect has strong analytical and reporting features as required by client
  • EnviroConnect has strong server component to handle large data load

Technical details of project and installation

Sr. No.

Category

Device Name

Parameters Measured

1

CEMS

Analyzer MGA 12

SO2,

CO,

CO2,

NO,

O2

2

Dust monitor PFM 02 V

Dust

3

Pressure Sensor

Pressure

4

Temperature Sensor

Temperature

5

Flow Meter

Flow

 

 

 

 

6

GLEMS (Ambient Station)

T 101

SO2

7

T 200

NOx

8

T 300

CO

9

T 400

O3

10

Weather station (AWS) sensors

Wind Speed,

Wind Direction, Sunshine,

Ambient temperature, Humidity,

Ambient Pressure

11

BAM 1020

PM 10

Currently the installation is complete for 6 sites. The good part about EnviroConnect is all the configuration and installation can be done remotely. Looking at the urgency in installation, all the required hardware was shipped and installed by GACS engineers. Our engineer completed installation of one site remotely and for another site visit and training purpose. Our engineer traveled to UAE and completed the installation.

 